The Twin Cities offer a favorable temperature and hydrogeologic environment for sustainable district energy using ATES. This presentation will review the challenges met in advancing a new ATES district energy project in Minneapolis. The technical, regulatory, and business milestones that have marked the progress of this project will be presented. The initial phase of the project is expected to require from 1-2.5 MW of thermal capacity from the wellfield, using four or six ATES wells.
Mark Worthington,CTO,Underground Energy, LLC
Sean McFarling,Sr. Engineer & CAD Supervisor,Ever-Green Energy
Jon Nunes,Lead Mechanical Engineer,Olsson
1800 West Park Drive, Suite 350
Westborough, MA 01581
Phone + (508) 366-9339
Fax + (508) 366-0019
© 2017 International District Energy Association, All Rights Reserved. Site by eConverse Media