This presentation discusses replacing aging turbine generators with two steam turbine generators at the University of Iowa’s Power Plant. This project modified the river water cooling system to increase heat rejection capabilities, reconfigured the plant steam system to reduce single point failure and upgraded the plant control system. Benefits of this project include more cost-effective electric generation, more system flexibility for adjusting to campus load swings, and added reliability for future outages.
Jeffery Gambrall, Senior Project Manager / Principal Electrical & Controls Engineer, PRVN Consultants Inc
Robert Murray, Program Manager, University of Iowa Capital Projects, ENGIE North America
1800 West Park Drive, Suite 350
Westborough, MA 01581
Phone + (508) 366-9339
Fax + (508) 366-0019
© 2017 International District Energy Association, All Rights Reserved. Site by eConverse Media