The University of Washington relies on its aging central plant for critical services. Meanwhile, the University’s sustainability goals are spurring a reevaluation of how the plant provides reliable energy. The Power Plant Infrastructure Renewal Project replaces aging plant equipment with a more reliable technology and contributes to the University’s sustainability goals. This presentation focuses on the selection of the Diesel Rotary UPS technology and the engineering challenges encountered during design.
John Solan, Principal Mechanical Engineer, Stanley Consultants
Mark Kirschenbaum,Assistant Director of Campus Utilities, University of Washington
Larry Johnson, Vice President, Stanely Consultants
#SystemExpansion,ModernizationandRenewal