The PJM Interconnection asked the Federal Energy Regulatory Commission on Tuesday to allow it to delay its May 2019 capacity market auction if the commission cannot make a final decision on rules for the market by early January.
PJM and its member states asked FERC last month​ for more time to respond to a June order invalidating the rules for PJM's capacity market. If FERC grants that deadline extension, PJM said it will need to delay the auction until August 14, 2019.
A delay in the capacity market auction would be "unusual but is not unprecedented," PJM said in a blog post. The 2015 auction, which provided power for the 2017-2018 delivery year, was pushed to August from May to provide PJM time to implement its capacity performance rules for generators.