Quebec community to be powered by biomass cogeneration plant

By District Energy posted 02-07-2023 14:51

  

Biomass Magazine

Summary

The Conseil des Atikamekw d'Opitciwan (CAO), Hydro-Québec (HQ) and the Société en commandite Onimiskiw Opitciwan (SCOO) have forged a historic agreement to build a forest biomass cogeneration plant to supply Opitciwan. The future off-grid system will be the first of its kind in an Indigenous community in Québec.

The agreement opens the door to the next stages of this project that's been long desired by the community. With an installed capacity of 4.8 MW, the plant is scheduled for commissioning in July 2026. The 25-year agreement, which has the option of a 15-year extension, also involves the acquisition and installation of a dryer at the Opitciwan