Think GeoEnergy
Summary
After a drilling period of two months, the drilling of production and reinjection wells for the second geothermal heating installation of Aardwarmte Vogelaer in the Netherlands has been completed. The second facility, which will supply geothermal heat to another 16 horticultural businesses, is expected to start operations by the end of 2025.
Drilling of the doublet for the expansion of the Aardwarmte Vogelear geothermal heating facility started in September 2023. However, well integrity and completion issues were encountered, necessitating the need to drill a sidetrack well. This suspended the work in December 2023, and operations resumed again on June 2025. A sidetrack was drilled from the reinjection well to about 2800 meters, and the production well was drilled to a total depth of about 3000 meters.