Industry News

 View Only

First offshore wind farm goes offline: An industry warning?

By Microgrid Resources Coalition posted 11-02-2020 15:57

  

Heather Richards and Arianna Skibell, E&E News reporters

Summary

In the new year, the first offshore wind farm in the United States will shut off its turbines, and its customers on nearby Block Island in Rhode Island will revert to diesel generation.

The rocky saeabed around Block Island has been worn away by tides and storms, sometimes exposing high-voltage cables in a popular swimming location that developers failed to bury deep enough when the facility was brought online in 2016. To splice in newly buried cables, the wind farm will go offline for a brief period this spring.

At $30 million for one leg of the fix and an undisclosed amount for the other, it's a costly problem to crop up for the nation's first offshore wind farm, and it's not totally isolated.

High-voltage lines that will be buried at sea to carry power from the burgeoning offshore wind sector and inject it into the onshore grid represent the most complicated, and as yet uncertain, aspect of an industry poised to boom, experts say. From grid congestion to technical troubles, the offshore wind's transmission challenge is the focus of growing attention as the industry advances.

"We cannot afford to develop the offshore grid in piecemeal," Judy Chang, the undersecretary of energy for the Massachusetts Executive Office of Energy and Environmental Affairs, said at a Federal Energy Regulatory Commission conference held on offshore's transmission challenges Tuesday.

Block Island represents just 30 megawatts of power, a pilot project that preceded what could be a wind boom driven by state commitments to buy offshore wind and decarbonize power systems.

Northeastern states that have made offshore wind procurements include Maine, Massachusetts, Rhode Island, Connecticut, New York, New Jersey, Maryland and Virginia, with a total of 6,460 MW selected and a goal of 28,530 MW.

Additionally, New York, New Jersey and Virginia are in the process of procuring another 7,540 MW cumulatively.

"We need a solid plan to ensure our offshore and onshore can work together to support that vision," Chang said.

But the overarching federal and state planning as voiced by Chang has been cautioned by others who are worried about constraining a nimble industry with regulations.

Others like WIRES Executive Director Larry Gasteiger say that rules and planning processes already exist that can accommodate the addition of offshore wind.

"The one outcome to avoid is any action, no matter how well-intentioned, that has the consequence of slowing down the development and integration of offshore wind resources," he said at the FERC conference.