MIT worked with Sega Inc. to upgrade its central utility plant DCS controls without ever going offline. Drivers included:

1) Needed upgrade for antiquated system.
2) Inability to find spare parts for maintenance and replacement efforts.
3) Difficulties around maintenance. 
4) Lack of experience technical support for older system. 

This presentation lays out what the MIT's system looked like before the project, how it changed, and discusses learnings from the effort. 

Speakers

Seth Kinderman, MIT
Dave Howell, Sega Inc.



#NorthAmerica #UnitedStates #SegaInc #MeteringandControls #CampusEnergyConference #Massachusetts #ConferenceProceeding #2016 #Optimization #MIT #DemandSideManagement

Statistics
0 Favorited
1 Views
1 Files
0 Shares
30 Downloads
Attachment(s)
pdf file
MIT Control Upgrades for Critical Utility Services   3.77 MB   1 version
Uploaded - 08-11-2017
Seth Kinderman, MIT Dave Howell, Sega Inc.