Over 80 percent construction progress for the cogeneration plant on the Petromidia platform

By District Energy posted 03-29-2023 15:44

  

The Diplomat

Summary

The Kazakh-Romanian Energy Investment Fund (KREIF) has made progress in commissioning the cogeneration plant on the Petromidia platform, reaching over 80 percent of the total operations, part of the project that started in May 2021.

Through Rompetrol Energy, member company of the KMG International Group (Rompetrol) and entity responsible for managing the energy projects carried out through the Fund’s mechanisms, KREIF managed to take new steps in completing one of the most important development projects.

The two heat recovery steam generators (HRSG) were delivered to the construction site near the refinery in Năvodari, each with a technological steam production capacity of 90 tons/hour plus additional combustion capacity.

“The project continues with a stable evolution, allowing us to fulfill, step by step, the proposed objectives. The most important equipment has arrived, is in position and we can say that the new energy production capacity on the Petromidia platform will use the latest cogeneration technologies. The created assembly will allow us to function as an element of streamlining the utilities used by the refinery, which will ensure its energy needs exclusively from the cogeneration plant”, said Boris Bucur, General Manager of Rompetrol Energy.