Summary 45 Rock housed a satellite plant with 30 y/o chillers. Study revealed opportunity to participate in utility demand management program, reducing peak demand at the Center. The plant was replaced with a 2,500 ton chiller plant and a 11,500 ton-hr ice storage plant integrated with a...
4C.2_Kain.pdf
ENR Southwest Summary Arizona State University Combined Heat & Power Facility Upgrade Tempe, Ariz. Best Project Owner/Developer: Arizona State University General Contractor: McCarthy Building Cos. Lead Design Firm, MEP Engineer: R.G. Vanderweil Engineers ...
Summary MIT has undertaken a 44 MW CHP plant expansion to address greenhouse gas emissions and improve system resiliency. The significant scale of this facility creates many challenges to be addressed by the project team including coordination of the required site aesthetics with the mission...
7A.3_Conklin_Thornton_Roveto.pdf
Summary Focus on water conservation in California, the district heating system needed to find a way to reduce boiler makeup water use. With a grant from City of San Francisco, participation from BART, NRG is installing new groundwater recovery system to a nearby subway station that could...
3D.2_Chiovoloni_Judd.pdf
Speakers Linda Hamdan, Vanderweil Engineers Michael Morehead #CampusEnergyConference #ConferenceProceeding #2014 #DistrictCooling #Vanderweil #SanFrancisco #California
3A.1_Hamdan_ Morehead.pdf
Speakers Chris Hastings, Vanderweil Engineers #AnnualConference #ConferenceProceeding #2014 #DistrictCooling #Vanderweil #AmmoniaRefrigeration #RiskMitigation
2B.1_Hastings.pdf
Speakers Bryce MacMartin, Vanderweil Engineers #AnnualConference #ConferenceProceeding #2014 #CHP #Vanderweil #ProjectPlanning
5B.3_MacMartin.pdf
Summary Mining and minerals separation plants with extensive chemical processes rely heavily on electrical power and require large quantities of high pressure steam. Yet, majority of these facilities are likely to be located in remote areas, far from reliable utility grid power sources,...
6A.2_Brooks, Demirchian.pdf
Summary The presentation highlights challenges and lessons learned from Algonquin Power's CHP installation project. Speaker Chistoper Hastings, Vanderweil Power Group #2015 #AnnualConference #ConferenceProceeding #CHP #Vanderweil #Industrial #MasterPlanningandSystemDesign ...
5A.3_Hastings.pdf
Summary The Problem Roles & Responsibilities Design-Bid-Build vs. Design-Build What Needs to Happen and When? Tools and Where To Get Them Top Lessons Learned Speakers Jeff Duncan, Vanderweil Engineers #AnnualConference #ConferenceProceeding #2014 #Vanderweil ...
2A.2_Duncan.pdf